The first 220-kilovolt submarine cable in the Beibu Gulf has been successfully laid.

December 31, 2025, saw the completion of a 44.8-kilometer 220-kilovolt submarine cable's cross-sea journey. As China's first such cable adopting domestically developed insulation materials, it braved 16 days of winds and waves, stretching from Weizhou Island in the Beibu Gulf to the submarine cable landing site on Beihai's coast. This marks the completion of the most critical part of the Southern Power Grid's 220-kilovolt Weizhou Island cross-sea interconnection project - the laying of the submarine cable. Weizhou Island has taken a step closer to achieving "direct power supply from the main grid".

Nestled in the central Beibu Gulf, Weizhou Island – Guangxi's largest island – lies 24 nautical miles off the mainland. For decades, it has operated on an isolated power grid, relying entirely on gas and diesel generators for electricity. In recent years, the tourism industry on the island has developed rapidly, with an average annual number of tourists exceeding 3 million. The limited public power supply has been unable to meet the electricity demands during peak periods such as the tourist season. In early 2025, the Guangxi Power Grid Company of Southern Power Grid invested 858 million yuan to initiate the construction of the first cross-sea interconnection project in the Beibu Gulf. It will build a 220-kilovolt Weizhou Substation on the island and construct a new 220-kilovolt line to the 220-kilovolt Dunhai Station in Beihai to connect to the main power grid system. On December 16, 2025, the cross-sea interconnection project entered the most complex and critical phase - the laying of the submarine cable. As the huge submarine cable laying vessel moved forward, the heavy cable weighing over 7,000 tons, like a "steel dragon", entered the sea floor, traveling along the predetermined route day and night, heading towards the landing point on the Beihai side.

 

Marine construction poses unique and daunting challenges, but the power grid team rose to the occasion. Equipped with state-of-the-art automated systems – including a full-rotation automatic control platform and real-time cable burial depth detectors – plus high-capacity towed underwater plows, they gained precise control over underwater operations. They achieved precise "threading and connection" on the sea floor and completed a series of high-difficulty constructions such as crossing multiple underwater pipeline intersections. To reduce the impact on the marine ecosystem, the construction team used the "three-dimensional geological modeling + precise directional drilling" technology to pass through the coral reefs from a depth of 25 meters below the sea surface, reducing the area of seabed disturbance by 85% compared to traditional construction. According to Qin Yi, the deputy manager of the substation of Guangxi Power Transmission and Transformation Company and the launch commander of the cross-sea interconnection project, the construction team will quickly carry out the protection joint commissioning of the 220-kilovolt Weizhou Substation, the connection of the submarine cable and the land cable, etc. It is expected that the overall project will be put into acceptance and operation in mid-to-late January 2026.

At that time, the power grid on Weizhou Island will be connected to the main power grid in Guangxi, with the power supply capacity increasing from 35,000 kilowatts to 161,000 kilowatts.The island will then have steady access to mainland electricity, where clean energy accounts for over 70% of installed capacity. This reliable green power supply will not only fuel the island's eco-friendly development and improve residents' lives, but also ensure seamless electricity for the booming tourism sector during peak seasons. In addition, the project can also meet the grid connection demand of offshore wind power in the vicinity of the island, providing a key transmission channel for future offshore wind power in the Beibu Gulf, and helping Guangxi build an energy new pivot point towards the sea.

220-kilovolt Weizhou Substation

 

 